Street & Bridge Projects

2019 Public Works Projects

Each year, the Board of Aldermen holds a budget discussion to prioritize city projects and services. After discussion and direction from the Board, the following projects were approved in the 2019
Budget.

Streets

The 2019 budget includes slabs, curb and cutter for Holloway Ridge Ct., Surf Ct., West Skyline (curb and gutter only), Oakwood Farms (Oakbriar to Jacob), Annondale, Coronado (concrete portion), Morewood (CDS to City Limit), Willowyek, Castle Pines Phase 2, West Glen Village (New Ballwin to Asphalt), Cross Hill, Eagles Glen South, and Fairway Lake. 

The budget also includes micropaving for Ramsey, Rethmeier, Woerther, Rasch Ct., Essen, Turfwood, Towerwood and mill/repaving for: Joyce Ct., Amber Jack Ct., West Skyline, Sweetwood Ct., and Sweetwood Ln.

Sidewalks

In conjunction with street resurfacing, sidewalks and curb ramps will be upgraded including Holloway Ridge, West Skyline, Fairway Lake, Oakwood Farms (Oakbriar to Jacob), Morewood, West Glen Village, and Castle Pines.

Project Updates

As of 1.28.19

The City of Ballwin plans to remove and replace deficient curb and gutters, and concrete pavement, and upgrade curb ramps to current ADA regulations on several streets in 2019. Below is a tentative schedule that will be updated periodically. All dates are estimated and subject to change based on weather conditions. Contractual jobs are indicated with an asterisk symbol.*

The City of Ballwin will also complete a number of projects in-house over the course of the year, thanks to the purchase of a new volumetric mixer. You can learn more about the new piece of equipment in the video below the list of projects.

Holloway Ridge Ct.* (Slab, Curb and Gutter, and Sidewalk Replacement) Work estimated to begin 7/1/2019
Surf Ct.* (Slab, Curb and Gutter Replacement) Work estimated to begin 7/1/2019
West Skyline* (Curb and Gutter, and Sidewalk Replacement) Work estimated to begin 7/1/2019
Oakwood Farms - Oakbriar to Jacob* (Slab, Curb and Gutter, and Sidewalk Replacement) Work estimated to begin 7/1/2019
Annondale* (Slab, Curb and Gutter Replacement) Work estimated to begin 7/1/2019
Coronado -concrete portion* (Slab, Curb and Gutter Replacement) Work estimated to begin 7/1/2019
Morewood - CDS to City Limit* (Slab, Curb and Gutter, and Sidewalk Replacement) Work estimated to begin 7/1/2019
Willowyek* (Slab, Curb and Gutter Replacement) Work estimated to begin 7/1/2019 
Castle Pines Phase 2* (Slab, Curb and Gutter, and Sidewalk Replacement) Work estimated to begin 7/1/2019
West Glen Village - New Ballwin to Asphalt* (Slab, Curb and Gutter, and Sidewalk Replacement) Work estimated to begin 7/1/2019
Cross Hill (Slab, Curb and Gutter Replacement) Work estimated to begin 7/1/2019
Eagles Glen (Slab, Curb and Gutter Replacement) Work estimated to begin 7/1/2019
Fairway Lake (Slab, Curb and Gutter, and Sidewalk Replacement) Work COMPLETED
Ramsey*  (Micropaving) Work estimated to begin 7/1/2019
Rethmeier* 
(Micropaving) Work estimated to begin 7/1/2019
Woerther*  
(Micropaving) Work estimated to begin 7/1/2019
Rasch Ct.* 
(Micropaving) Work estimated to begin 7/1/2019
Essen* 
(Micropaving) Work estimated to begin 7/1/2019
Turfwood* 
(Micropaving) Work estimated to begin 7/1/2019
Towerwood* 
(Micropaving) Work estimated to begin 7/1/2019
Joyce Ct. (Mill and repaving) Work estimated to begin 7/1/2019
Amber Jack Ct. (Mill and repaving) Work estimated to begin 7/1/2019
West Skyline 
(Mill and repaving) Work estimated to begin 7/1/2019
Sweetwood Ct. 
(Mill and repaving) Work estimated to begin 7/1/2019
Sweetwood Ln. 
(Mill and repaving) Work estimated to begin 7/1/2019

  

 

 

ADA Sidewalk Transition Plan

The Americans with Disabilities Act (ADA) law requires public entities to develop a formal transition plan identifying the steps necessary to meet ADA accessibility requirements for all pedestrian access routes by upgrading all noncompiliant features.  The Street Transition Plan (PDF below) is attached that was adopted by the Board of Aldermen on February 27, 2017.

The Plan includes when, how, and where curb ramps and sidewalks will be updated to current ADA standards.  All curb ramps will be upgraded when a street is overlaid, resurfaced, microsurfaced, or reconstructed.  All new sidewalks will be constructed in accordance with the ADA regulations.  Uneven sidewalks are to be eliminated in a timely manner.

ADA Sidewalk Transition Plan

Ballwin Public Works Department
(636) 227-9000