Street & Bridge Projects

2018 Public Works Projects

Each year, the Board of Aldermen holds a budget discussion to prioritize city projects and services. In October of 2017, a budget session was held to discuss how to best use projected revenues to benefit our residents in 2018. During the discussion, the Public Works Department presented recommendations on street repairs and projects.

After further discussion and direction from the Board, the following projects were approved in the 2018
Budget.

Streets

The 2018 budget includes resurfacing Windcliffe (asphalt over concrete portion), Royal Oaks, Manorcrest, Ironwood, Sunstone, and Old Ballwin Road. Selected concrete pavement replacement has also been
budgeted on Windcliffe (concrete portion), Orkney, Fieldstone, Trailwood, Caprice Gardens, Oakwood Farms Phase 1 (dead end-Oakbriar Farm), Castle Pines-Phase 1, Old Ballwin Road (Curb & Gutter), Kehrs Mill Trail, Holloway Ridge Ct, Village Meadows, Wetherburn, and Fairway Lake.

Sidewalks

In conjunction with street resurfacing, sidewalks and curb ramps will be upgraded to meet current ADA
standards. Work is expected to begin in March or April depending on weather.

The cities of Ballwin and Ellisville will share the cost in 2018 to reconstruct 650 feet of Reinke Road east of the new roundabout. This project will improve the roadway curves and sight distances.

Project Updates

As of 6.5.18

The City of Ballwin has awarded a contract to M&H Concrete Contractors to remove and replace deficient curb and gutters, and concrete pavement, and upgrade curb ramps to current ADA regulations on several streets. Below is a tentative schedule that will be updated periodically. Contractual jobs are indicated with an asterisk symbol. 

The City of Ballwin will also complete a number of projects in-house over the course of the year, thanks to the purchase of a new volumetric mixer. You can learn more about the new piece of equipment in the video below the list of projects. City staff will work to eliminate sidewalk tripping hazards toward the later half of the construction season.

Caprice Gardens Drive (Sidewalk Replacement) Start date TBD
Caprice Gardens Drive* (Slab and Sidewalk Replacement) Completed
Castle Pines Drive (Sidewalk Replacement) Start date TBD
Castle Pines Drive* (Slab and Sidewalk Replacement) Slab completed, sidewalk start date TBD
Country Club (Sidewalk replacement) Start date TBD
Downall Green (Slab replacement) Start date TBD
Fairway Lake (Slab replacement) Start date TBD
Fieldstone Drive (Sidewalk Replacement) Start date TBD
Fieldstone Drive* (Slab Replacement) Completed
Henry Road (Sidewalk replacement) work in progress
Holloway Ridge Court (Slab and sidewalk replacement) Tentative start date end of June, 2018
Kehrs Mill Trail (Slab replacement) work in progress
Newfield Ct Circle (Sidewalk replacement)
Oakwood Farms Drive (Sidewalk Replacement) Start date TBD
Oakwood Farms Drive* (Slab Replacement) work in progress
Old Ballwin Road* (Curb & Gutters, Sidewalk Replacement) work in progress (approximately half way done)
Old Woods Mill (Drainage pipe) Work in progress
Orkney Court (Sidewalk Replacement) Start date TBD
Orkney Court* (Slab Replacement) Completed
Ries Road (Sidewalk replacement) Tentative start date TBD
Trailwood Drive (Sidewalk Replacement) Start date TBD
Trailwood Drive* (Slab Replacement) Completed
Village Meadows (Slab replacement) work in progress
Weatherburn (Slab replacement) Start date TBD
Windcliffe Drive (Sidewalk Replacement) Start date TBD
Windcliffe Drive* (Slab Replacement) Work in progress

Reinke Road Project

July 12, 2018

RE: Reinke Road Improvement Project Roundabout, East to 822 Reinke Road

Dear Ballwin Resident:

The City of Ballwin and the City of Ellisville have partnered together to complete street improvements on Reinke Road from the new roundabout, east to 822 Reinke Road. The projected improvements will include relocation of the existing street to straighten out the street and improve sight distance. The improvements will include construction of a twenty-nine foot wide asphaltic concrete street with concrete curb and gutter, sidewalk, underdrains, modifications to the existing storm water system, new driveway approaches and other miscellaneous items such as grading and sodding.

L. Krupp Construction, Inc. has been awarded the contract for the project. Work is planned to start on August 13, 2018, weather permitting. Working hours for the contractor will be from 7:00 a.m. to 5:00 p.m., Monday through Friday. This work will take approximately two months to complete. Reinke Road will remain open during the project. The contractor will schedule the street work in four phases to minimize the amount of inconvenience to property owners and always allow access to Reinke Road. Enclosed are maps showing the four different phases of the construction for the Reinke Road improvements.

Before work begins, all of the utility companies such as Spire, Missouri-American Water Company, Charter Communications, Ameren UE and AT&T will be locating their facilities to insure that they are not disrupted during the street reconstruction work. Usually, these facilities are located with paint marks or small flags. It is very important that these marks not be disturbed since they will be used by the construction crews throughout the street improvement project. In addition, survey crews will be installing wood stakes to mark the location of the new storm sewers and the edges of the new roadway.

Please drive slowly and obey all traffic signs in the work areas. All disturbed areas will be backfilled with earth and rough graded. Once the street improvements are completed, these areas will be fine graded and restored to their original condition.

The City of Ballwin and the City of Ellisville appreciate your patience and cooperation during this work. Should you have any questions or need additional information, please contact at 636-227-9000.

Sincerely,

Andy K. Hixson ICMA-CM Dir. of Development/Assistant City Administrator

Jim Link Superintendent of Streets

 

Bridge Replacements

Updated 5.14.18

Two bridges over Fishpot Creek will be replaced in 2018. The first to be replaced is on Ries Road between Manchester Road and Ramsey Lane. The other bridge is on Ramsey Lane just south of Manchester Road.

The Federal Highway Administration will reimburse the City 80% of the cost for both bridges. At their April 9, 2018 meeting the Board of Aldermen awarded contracts to KCI Construction for the construction of both bridges.

Ries Road will be closed at the creek beginning in the morning on Friday, May 25 (pushed back from original date of May 23). Detour signs will direct motorists to Sulphur Springs Road, New Ballwin Road, and Ramsey Lane until the bridge is reopened. The reopening is expected in September 2018. A detour map is available showing these alternate routes. Please revisit this webpage or follow the Ballwin Public Works Department Facebook page for updates. If you have any questions you may contact Director of Public Works Gary Kramer at 636-227-2185 or by email at .

Once this bridge is reopened to traffic, the Ramsey Lane Bridge will be closed.  The new Ries Bridge will consist of precast concrete arches with a sidewalk along both sides. Decorative wrought iron style fencing will be added for pedestrian safety. A concrete barrier will separate pedestrians and vehicles as they cross the bridge.

Ramsey Lane Bridge is expected to close in August and reopen in December 2018. Traffic will be detoured via Ries Road, Sulphur Springs Road, and New Ballwin Road.  The new bridge will consist of precast concrete girders.  Sidewalks, wrought iron style fencing, and concrete barriers are also included along both sides.

 

ADA Sidewalk Transition Plan

The Americans with Disabilities Act (ADA) law requires public entities to develop a formal transition plan identifying the steps necessary to meet ADA accessibility requirements for all pedestrian access routes by upgrading all noncompiliant features.  The Street Transition Plan (PDF below) is attached that was adopted by the Board of Aldermen on February 27, 2017.

The Plan includes when, how, and where curb ramps and sidewalks will be updated to current ADA standards.  All curb ramps will be upgraded when a street is overlaid, resurfaced, microsurfaced, or reconstructed.  All new sidewalks will be constructed in accordance with the ADA regulations.  Uneven sidewalks are to be eliminated in a timely manner.

ADA Sidewalk Transition Plan

Ballwin Public Works Department
636-227-9000